Rochedale Rd: 4-Lot Subdivision

With 2 street frontages, there was an opportunity to subdivide this land into 4 lots. 

Issues that we had to navigate included access from Rochedale Rd, which is a major road and demonstrate how access would work via the cul-de-sac frontage.  

following achieving town planning approval we were engaged to project manage the delivery of the subdivision. 
 
Our responsibilities included:
 
– developing and implementing a full project plan
– budgeting and costs
– tendering
– civil contractor selection
– management of civil contractor, electrical contractors and civil engineer.
 
The project also required liaison with SARA/TMR for bus stop relocation.
 
A partial road closure was required to relocate the bus stop and complete civil works.
 

Year: 2023-24

Project: 4-Lot Subdivision

Council: Logan City

Services: Town Planning | Project Management